This project is read-only.

Summary PBIs

Oct 18, 2013 at 8:03 PM
We are trying to use TFS Workbench but we are using summary SBT's. Let me give an example

PBI--
  |
   SBT--
          |
           SBT
So the problem we have is when we look at the task board we see the first level SBTs but the second levels all show up under Other Items, Orphan Items.

Is there any way in the current system to represent this kind of setup?

Thanks
Oct 22, 2013 at 8:16 PM
Edited Oct 22, 2013 at 8:17 PM
I don't believe the SfTS process template is intended to support this concept. Even in the most recent TFS tools this can be an issue.
Oct 22, 2013 at 8:24 PM
Yes I have since figured this out but I cannot get my developers to use it without the summary tasks.

I can understand why they want them but I can see that they are not needed either.

Thanks for the Reply!