Burndown not showing Trendline or Capacity line (v3, TFS2010)

Apr 4, 2012 at 6:20 PM

Our burndown charts show up on our portal and in Episerver scrum dashboard V3, but the capacity and trend lines don't paint on the reports.

Interestingly enough, even in the process guidance documentation for the burndown, the capacity and trend lines show in the legend but not in the chart screenshot on the page:

http://www.scrumforteamsystem.co.uk/ProcessGuidance/v3/sprint%20burndown%20chart

 

Any idea how to fix this?  It's really causing the burndown to be ineffective at giving us an at-a-glance look at progress and forecast.

 

Apr 5, 2012 at 9:33 AM

The burndown in the guidance shows a completed burndown which doesn't show the trend or capacity lines. However you may well be hitting a problem in the report that has a fix to the rdl indicated in this thread: http://www.scrumforteamsystem.co.uk/QA/Show?id=294