User Story Remaining hour

Oct 18, 2012 at 11:04 PM

We are having issue with user story remaining hour not in sync with total task hour.

For Ex: 5 task in a user story, out of which 1 task = 8 hrs, rest zero. but the sum up amount of task hour in remaining hour shows up as 144. where it should be equal to 8 hrs?

we are using scrum v2 with tfs 2010. Any help/advice/suggestion

Oct 19, 2012 at 6:06 AM

The event service is broken by TFS 2010, but there is a replacement. See http://consultingblogs.emc.com/crispinparker/archive/2011/01/07/scrum-for-team-system-v2-projects-in-tfs-2010.aspx.

Oct 19, 2012 at 5:10 PM

Thanks for the reply.