I am trying to track down an issue where the History Date (Scrum v3) does not get correctly updated.

Most items are correctly changed:

12/14/2011 9:43:15 AM Edited (Not Started to In Progress) by <<REDACTED>>

Field Old Value New Value
State
Not Started
In Progress
Rev
8
9
History Date (Scrum v3)
12/14/2011 8:44:54 AM
12/14/2011 9:43:04 AM
Reason
New
Work has commenced

But every once in a while, this happens:

12/15/2011 4:31:13 AM Edited by <<REDACTED>>

Field Old Value New Value
Rev
9
10
History Date (Scrum v3)
12/14/2011 9:43:04 AM
12/14/2011 9:43:13 AM
Work Remaining (Scrum v3)
4
2

Any ideas why this might happen?